Construction Laborer how-to

How to Place and Finish a Small Concrete Slab

Concrete work moves fast once the truck arrives. Preparation is everything.

Updated By the Career Education Institute Curriculum Team
Quick answer

Concrete work moves fast once the truck arrives. Preparation is everything. In short: check; wet; place, then complete the remaining steps below.

Step by step

  1. Check that forms are secure and level and that the base is compacted.

  2. Wet the base slightly if dry so it doesn’t pull water from the concrete.

  3. Place concrete close to its final position: don’t drag it long distances.

  4. Spread with a come-along or rake and consolidate to remove air pockets.

  5. Screed the surface with a straightedge resting on the forms.

  6. Bull float to smooth the surface, then wait for bleed water to evaporate before final finishing.

  7. Edge, joint and broom finish as specified, then begin curing.

Safety reminders for construction laborers

  • Never enter a trench five feet or deeper without a protective system approved by a competent person
  • Use fall protection at heights of six feet or more on construction sites
  • Wear high-visibility apparel near traffic and moving equipment
  • Control silica dust with water or vacuums and wear respiratory protection when required

OSHA 10 · Competent person · Trench box · Shoring · Rebar · Formwork: see the full construction laborer glossary.